DOUGLAS
E. SMITH
Smith Custom Builders
There
are many different types of foundation systems used in the tfouston area,
such as Slab-on-grade, Pier and Beam, Void-Box, Crawl Space with or without
Piers, Post- Tensioned and Driven Pile. But do not be confused, the decision
on which to use will come from the soil report, structural engineer and
your budget.
Just as important as choosing the proper foundation is the
evaluation and preparation of the site before the foundation work begins.
First, one should contact a geo- technical company to evaluate
subsurface soil conditions. To compile the information for their "soil
report," the geotechnical company must perform one or more borings.
A boring is a 2- to 3-inch diameter, 15- to 20 foot deep soil
sample that the geotechnical company will take back to the lab to evaluate.
The company will then write the soil report based on their findings. The
evaluation develops recommendations to the structural engineering firm
to determine and design the foundation system best suited for the lot.
Next, the engineer reviews the flood plain maps provided by
FEMA. This is necessary to determine the top of slab or finished floor
elevation. The pad site is the area of select fill dirt that is built
up beneath the slab.
Pad thickness will determine the final top of slab (or floor)
elevation. Select fill is dirt that has a very low percentage of clay
and that can be compacted to desired percentage.
Builders now have the select fill placed in "lifts,"
meaning 8 inches of select fill is gathered and compacted to 6 inches.
This process is repeated until the desired pad height is reached. Compaction
tests are done throughout this process by the geotechnical com- pany,
measuring the density of the soil after it is compacted.
|
|
-
Post Tensioned Foundations are very commonly used. They utilize high-tension
cables, which are hydraulically tightened after the concrete has hardened,
giving the slab its ability to hold together under most ground movement.
This is usually the most economical type available.
- A Pier-and-Beam Foundation System uses drilled piers
at a depth determined by the soil report. The pier is a concrete-filled
cylindrical hole, at least 12 inches in diameter, usually with a 36-inch
belled bottom. Grade beams are placed on top of these piers, and in turn
support a slab -typi- cally 4 inches thick.
- A structural (void-box) slab is an enhanced version of the
pier-and-beam foundation, and has very thick, wax-coated, cardboard spacers
between the grade beams under the slab. This is called the "crush
zone," because uplift from swelling caused by in- creased moisture
content in the clay-based soil crushes the void boxes, but without lifting
the slab off the grade beams and piers.
- Crawl Space Foundation can be detailed in different ways. Depending
on the soil report, you can have a combination of drilled piers and grade
beams, or just one of these types alone. I prefer to use the combination.
On top of piers or grade beams you can have blocks, or the
pier can extend above the ground level to the desired height. Above this
level, beams (stringers), trusses or 2-by-12 joists can be used to support
the finished floor. This is a typical system throughout the Historical
Heights area.
The last test required is the concrete strength test. During
the foundation pour, plastic cylinders are filled with concrete. These
cylinders are sent to the geotechnical company to break at 7 and 28 days.
These tests show if the concrete mixture used falls within the engineered
guidelines, usually a minimum of 3,000 pounds per square inch in 28 days.
|
Following
these tests, the surveying company determines the actual corner points
of the foundation. They also set the benchmark, a marker that is used
to establish the final foundation and slab elevation, relative to existing
grade.
Two very critical
inspections must be done before concrete is poured. One is the pier hole
inspection; another is the complete foundation makeup.
These inspections are usually preformed by the city inspector
along with a representative from the engineering company.
Most builders obtain a letter from the engineering firm, stating
that the builder has assembled the components accord- ing to plans and
specs.
In city municipalities, permission to pour concrete is not
usually given until the builder provides the city inspectors with copies
of compaction tests and the engineer's inspection letters.
The most common types of foundations used in the Houston areas
are:
- Slab On Grade can be built with grade beams or without. If grade
beams are not used, the slab is usually poured much thicker than the usual
4 inches. Grade beams are usually 24- to 36-inch-deep, and 12- to 16-inch-
wide trenches in the ground, with reinforcing bar {rebar) running the
length of the beams.
Rebar is the steel in the concrete, which bonds it together
and helps the concrete achieve its strength. Grade beams give the slab
its strength and stiffness. If beams are not used, the slab can break
easier with ground move- ment. The engineering firm determines grade beam
height and width, as well as reinforcement.
|